Budget (Cash/Hours) "current prediction" values on reports
On the reports it would be good to introduce a "predicted" calculation for all of the current budget views on scheduled/reported that combines reported to date and scheduled future.
I.e.
If my project budget is 100 hours.
and in the 1st week I schedule 50 hours
and in the 2nd week i schedule 40 hours
but i only report 45 hours in the 1st week.
When viewing the report on the start of the 2nd week is would like to see a predicted spend based on reported to date plus scheduled future e.g. in this case showing 85 hours, 15 remaining.
Currently i don't believe it's possible to view the 85/15 figure, only to see the 90(scheduled)/10(remaining) originally scheduled and the 45(reported)/55 (reported remaining) actually reported.
-
This has now been completed. You will locate the columns called Estimated.
Thanks,
Team Hub Planner -
Hi,
Many thanks for taking the time to submit your suggestion for a new reports column.
Request for column that calculates: Reported Spend/Time to Date + Scheduled Spend/Time Future.
We will endeavour to post this to the developer back log on reports.
Best
Team Hub Planner